Significant expansion of Queenstown Airport car parking in time for busy summer season
14 Oct 2016

Queenstown Airport will embark on expansion works today (Friday 14 October) to its short and long term car parking facilities creating a significant number of additional car parking spaces.
Due for completion by 29 November, in time for the busy summer season, the staged expansion works will provide approximately 50 additional car parking spaces to meet customer needs – an increase of over 10%.
Works to expand the commercial zone also commenced this week which will enable both pick-up and drop-offs for commercial operators in this zone. This work will be completed by 27 October.
To take account of the potential inconvenience to customers, we have reduced our car parking rates for the period of works in the long term car park (14 October – 3 November) for the majority of our car parking customers. Normal rates will resume once the long term car park re-opens on 4 November.
Queenstown Airport Corporation (QAC) CEO Colin Keel said the works formed part of the airport’s short term infrastructure improvement programme.
“The airport has experienced phenomenal growth with a 38% rise in passenger numbers over the past three years alone. This growth has presented us with a range of opportunities and challenges, including the increased need for car parking.”
“We’re actively listening to the communities that we serve on these issues and have taken their views on board. We’re committed to providing an exceptional and memorable customer experience for all our visitors.”
“The works have been scheduled at a quieter time of year to ensure minimal impact on visitors, staff and the broader airport community and will be completed in a very short time frame to minimise any disruption,” said Colin.
The works are also a prelude to the airport’s long term strategy on traffic management and road transport solutions which will improve traffic flow and further increase car parking options.
“These are key focus areas as we develop the 30-year master plan for Queenstown Airport.”
“Our contractors and staff will be actively monitoring and managing the expansion plans to ensure it’s as seamless as possible for our customers. There will be temporary signage in place to help guide drivers and staff will be outside directing traffic at all times.”
Full details and timeline of the planned works can be found below.
What's Happening | When |
Stage 1 – Commercial Area staged work |
14 -27 October |
Stage 2 – Long Term Car Park - Entry Closed Off and works |
14 – 25 October Closed to vehicle entry 25 October – 3 November works |
Stage 3 – Staged expansion of short term car park |
1 – 29 November |
Overflow Parking |
14 October – 29 November |
Other News
- QAC Chief Executive announces resignation
- Queenstown Airport welcomes quarantine-free travel with Australia
- Queenstown Airport gearing up for the Easter long weekend
- Queenstown Airport welcomes COVID-19 vaccination rollout
- Queenstown Airport Corporation reports half-year results
View All News